The following costs are for the development of community sports
facilities and are based on providing good quality sports
facilities for the 2nd quarter 2011. These rounded costs
are based on typical schemes funded through the Lottery, or CAD
layouts being developed in accordance with Sport England DGN’s
current at 2nd quarter 2011.
New work output is forecast to fall a little in 2011 as the cuts
in public sector spending start to make their mark, partly
mitigated by private sector output starting to recover more
strongly. It is anticipated that there will be a return to sluggish
growth in 2012, as public sector cuts deepen.
The BCIS forecast is for tender prices to rise
by 2.8% in the year to 4th quarter 2011, rising by 3.1%
over the following year.
|
Facility Type
|
|
Facility Details
|
|
Area
(m2)
|
|
Capital
Cost
|
|
Sports Hall
|
|
1 Court (18 x 10)
|
|
373
|
|
800,000
|
|
|
|
2 Court (18 x 17)
|
|
510
|
|
930,000
|
|
|
|
3 Court (27 x 18)
|
|
990
|
|
1,805,000
|
|
|
|
4 Court (33 x 18)
|
|
1,435
|
|
2,685,000
|
|
|
|
6 Court (34 x 27)
|
|
1,758
|
|
3,170,000
|
|
Pools
|
|
25m Pool 4 Lane (25 x 8.5)
|
|
1,140
|
|
2,890,000
|
|
|
|
25m Pool 5 Lane (25 x 10.5)
|
|
1,238
|
|
3,120,000
|
|
|
|
25m Pool 6 Lane (25 x 12.5)
|
|
1,419
|
|
3,410,000
|
|
|
|
25m Pool 8 Lane (25 x 17)
|
|
1,803
|
|
4,450,000
|
|
Pavilion/Club House
|
|
2 Team Pavilion and Club House
|
|
100
|
|
250,000
|
|
|
|
4 Team Pavilion and Club House
|
|
300
|
|
575,000
|
|
Indoor Bowls Centre
|
|
6 Lane
|
|
1,914
|
|
1,640,000
|
|
|
|
Extra Lane
|
|
|
|
220,000
|
|
Bowling Green
|
|
Flat or Crown Green (40 x 40)
|
|
1,600
|
|
110,000
|
|
Indoor Tennis Centre
|
|
3 Court
|
|
2,138
|
|
1,850,000
|
|
|
|
Extra Court
|
|
|
|
610,000
|
|
Outdoor Tennis Court
|
|
2 Court Macadam, Fenced and Floodlit, courts
36.58x33.53
|
|
1227
|
|
145,000
|
|
|
|
4 Court Macadam, Fenced and Floodlit, 36.58 x
64.01
|
|
2342
|
|
275,000
|
|
Grandstand
|
|
500 Seats with no Under Croft
|
|
|
|
510,000
|
|
Skate Park
|
|
40 x 18m Fenced and Floodlit
|
|
720
|
|
120,000
|
|
Athletics Track
|
|
6 Lane Floodlit, 110 straight both sides,
grass infield, artificial throws, jumps and end fans
|
|
|
|
1,080,000
|
|
|
|
8 Lane Floodlit, 110 straight both sides,
grass infield, artificial throws, jumps and end fans
|
|
|
|
1,175,000
|
|
Multi Use Games Area
|
|
36.60 x 21.35 Fenced and Floodlit
|
|
782
|
|
115,000
|
|
Grass Pitch
|
|
U8/U7 Mini Football (53.04 x 34.75)
|
|
1,843
|
|
25,000
|
|
|
|
U16/U15 Youth Football (98.76 x 62.18)
|
|
6,141
|
|
65,000
|
|
|
|
Senior Football (107.90 x 71.33)
|
|
7,697
|
|
75,000
|
|
|
|
Rugby League (128.00 x 74.00)
|
|
9,472
|
|
90,000
|
|
|
|
Rugby Union (154.00 x 80.00)
|
|
12,320
|
|
115,000
|
|
|
|
Cricket Pitch, with 8 pitch square and 2
winter sport pitches (126.12 x 167.06)
|
|
21,070
|
|
200,000
|
|
Synthetic Turf Pitch
|
|
U8/U7 Mini Football/Training (23mm Sand
Filled, Fenced and Floodlit) (61.0 x 42.6)
|
|
2,599
|
|
350,000
|
|
|
|
U8/U7 Mini Football/Training (40 -50mm 3G,
Fenced and Floodlit) (61.0 x 42.6)
|
|
2,599
|
|
370,000
|
|
|
|
U8/U7 Mini Football /Training (60 -65mm 3G,
Fenced and Floodlit) (61.0 x 42.6)
|
|
2,599
|
|
380,000
|
|
|
|
Hockey Pitch (18mm Sand Dressed, Fenced and
Floodlit) (101.4 x 63.0)
|
|
6,388
|
|
690,000
|
|
|
|
Hockey Pitch (23mm Sand Filled, Fenced and
Floodlit)
(101.4 x 63.0)
|
|
6,388
|
|
640,000
|
|
|
|
Hockey Pitch (Water Based, Fenced and
Floodlit)
(101.4 x 63.0)
|
|
6,388
|
|
815,000
|
|
|
|
Senior Football (23mm Sand Filled, Fenced and
Floodlit) (106 x 71)
|
|
7,526
|
|
730,000
|
|
|
|
Senior Football (40mm 3G, Fenced and
Floodlit)
(106 x 71)
|
|
7,526
|
|
790,000
|
|
|
|
Senior Football (50mm 3G, Fenced and
Floodlit)
(106 x 71)
|
|
7,526
|
|
810,000
|
|
|
|
Senior Football (60mm 3G, Fenced and
Floodlit)
(106 x 71)
|
|
7,526
|
|
830,000
|
|
|
|
Senior Football (65mm 3G, Fenced and
Floodlit)
(106 x 71)
|
|
7,526
|
|
840,000
|
|
|
|
Rugby League (65mm 3G, Fenced and
Floodlit)
(120 x 75)
|
|
9,000
|
|
1,070,000
|
|
|
|
Rugby Union (65mm 3G, Fenced and Floodlit)
(130 x 80)
|
|
10,400
|
|
1,185,000
|
|
|
|
Cricket Practice Strip, macadam surfaced with
batting cage (32 x 3)
|
|
96
|
|
30,000
|
Note1. The Area for “Buildings” is the Gross
Internal Floor Area (GIFA).
Note2. The Area for Pitches typically includes
Safety Run Offs.
Note3. Sizes given for artificial and grass
pitches reflect developing Best Practice or NGB
recommendations.
The costs include allowances for the
following:
- External
works (car parks, roads, paths, services connections etc) are
included at an average of 15% in addition to the costs of the
works
- 12 months
maintenance/grow in costs for Grass Pitches.
Fees are included at 12.5% (inclusive of PM,
SI, Planning and associated Fees) for;
- Sports
Halls
- Pools
-
Pavilion/Club House
- Indoor
Tennis Centres
- Indoor
Bowls Centres
-
Grandstands
Fees are included at 6% (inclusive of PM, SI,
Planning and associated Fees) for;
- Synthetic
Turf Pitches
- Multi-use
Games Areas
- Athletics
Tracks
- Outdoor
Tennis Courts
- Grass
Pitches
- Bowling
Greens
The costs exclude the following:
- Project
specific details/information, including poor ground conditions,
difficult access, long service connections
- Grass
pitches exclude the costs for site remodelling, pump and sump
systems and SUDS attenuation
- Inflation
beyond current 2Q2011 prices
- VAT
- Land
acquisition costs
- Regional
cost variations in materials and labour